North Sea Well Access Restored Through Intelligent Wireline Intervention Well-Safe Solutions Recovers 11,575 ft of Slickline Lost in a Well After 15 Years Collection of data with minimal pressure loss in flowing wells Contingency barrier option on high-value subsea wells Recovery of magnetic junk in high temperature wells Hard scale removal at multiple obstruction points Retrieval of equipment lost in the well and fast-track production restart High deviation, heavy-duty fishing, North Sea Recovery of safety valve lockout tool which had parted downhole Retrieval of sub-surface safety valve (SSSV) with damaged fish neck Retrieval of injection valve backed off from 7-in retrievable bridge plug Trial deployment of slickline-set SIM plugs and Peak latch/seal micro coil stinger Data acquisition to monitor pressure buildup in a shut-in well Bespoke activation tool design Evaluation of an e-line deployed tractor, stroker, and slickline toolstring Trial test to remove hard scale from production tubing using mechanical means Cut wire at rope socket to retrieve stuck toolstring Retrieval of injection valve from tubing crossover at 10,400 ft High-deviation fishing at depth in the Middle East Isolation of failed inflow valve at high deviation Location and stabilization of a leak path in the completion string Innovative use of an LWIV to perform first subsea slickline intervention in Nigeria Efficient straddle solution enables repair of production Christmas tree Permanent plug keeps P&A project moving Peak eCutter facilitates faster stuck toolstring recovery in long-reach, highly-deviated well Retrievable sand screen anchoring system eliminates leaks Mechanical scale removal saves USD 250,000 PTTEP gas lift straddle conversion restores oil production for mature well Slickline-deployed plug isolates damage to avoid workover KOC restores oil production to 800 bbl/d using digital-slickline-conveyed straddle system D-Set setting tool and DSL digital slickline cable set large-bore gauge hanger in monobore well > Retrievable bridge plug enables proper tubing cut and saves 4 rig days, Congo Remote Intervention Operation Enables Effective Planning of Plug and Abandonment Campaign Shell Removes 900-ft Parted Wireline from North Sea Well Setting a Critical Well Barrier in Tubing with Damaged Nipple Profiles

Retrievable bridge plug enables proper tubing cut and saves 4 rig days, Congo

Rigless intervention reduces workover cost and mitigates risk.

SIMultra plugs have a high expansion ratio, expanding and retracting significantly further than conventional V0-rated sealing technologies. The SIMultra retrievable bridge plug saved 4 rig days during an intervention operation in HPHT environment.

The operator's goal

A gas injector well was to be converted into a producer well. A workover program was planned to cut and change the existing tubular, including setting a standard plug to isolate the lower zone.

The wellbore had a 75° deviation at 4,283-m [14,052-ft] MD with a minimum restriction of 4.313 in at the nipple. The lower-profile sealbore provided an insufficient barrier and limited the deep-set plug development for the lower zone. And additional risks involving a severing operation, which had blocked the retrieving process, were identified.

The operator needed to create a gas-tight seal in a 5½-in, 320-kg/m3 [20-lbm/ft3] liner in a challenging HPHT environment with pressures up to 35 MPa [5,076 psi] and temperatures up to 152 degC [306 degF]. To minimize workover time and cost, alternative e-line rigless intervention options were pursued.

What was tried first

Traditional deep-set plugs did not meet the expansion requirement for the current working envelope, and a cementing operation was not a viable option to provide a consistent and homogenous barrier at such deviation and temperature.

What Schlumberger recommended

The SIMultra retrievable bridge plug was deployed using the TuffTRAC cased hole services tractor. Certified to ISO 14310:2008 grade V0 and quality grade Q1, the SIMultra retrievable bridge plug incorporates a proprietary hybrid metal-elastomer seal to create a well barrier with both exceptional reliability and retrievability. Suited for HPHT operations, it is performance rated to 177 degC [350 degF], 69 MPa [10,000 psi], and extreme CO2 sour service capability.

Using metallic support plasticity to close the extrusion gap during the setting process, the elastomeric compound of the historically high shearing stress is freed—unlocking sealing performance to a completely new stage.

What was achieved

The successful gas-tight isolation using the SIMultra plug enabled cutting the tubing properly, and the rigless intervention saved 4 rig days, reducing workover costs.

 