North Sea Well Access Restored Through Intelligent Wireline Intervention Well-Safe Solutions Recovers 11,575 ft of Slickline Lost in a Well After 15 Years Collection of data with minimal pressure loss in flowing wells Contingency barrier option on high-value subsea wells Recovery of magnetic junk in high temperature wells Hard scale removal at multiple obstruction points Retrieval of equipment lost in the well and fast-track production restart High deviation, heavy-duty fishing, North Sea Recovery of safety valve lockout tool which had parted downhole > Retrieval of sub-surface safety valve (SSSV) with damaged fish neck Retrieval of injection valve backed off from 7-in retrievable bridge plug Trial deployment of slickline-set SIM plugs and Peak latch/seal micro coil stinger Data acquisition to monitor pressure buildup in a shut-in well Bespoke activation tool design Evaluation of an e-line deployed tractor, stroker, and slickline toolstring Trial test to remove hard scale from production tubing using mechanical means Cut wire at rope socket to retrieve stuck toolstring Retrieval of injection valve from tubing crossover at 10,400 ft High-deviation fishing at depth in the Middle East Isolation of failed inflow valve at high deviation Location and stabilization of a leak path in the completion string Innovative use of an LWIV to perform first subsea slickline intervention in Nigeria Efficient straddle solution enables repair of production Christmas tree Permanent plug keeps P&A project moving Peak eCutter facilitates faster stuck toolstring recovery in long-reach, highly-deviated well Retrievable sand screen anchoring system eliminates leaks Mechanical scale removal saves USD 250,000 PTTEP gas lift straddle conversion restores oil production for mature well Slickline-deployed plug isolates damage to avoid workover KOC restores oil production to 800 bbl/d using digital-slickline-conveyed straddle system D-Set setting tool and DSL digital slickline cable set large-bore gauge hanger in monobore well Retrievable bridge plug enables proper tubing cut and saves 4 rig days, Congo Remote Intervention Operation Enables Effective Planning of Plug and Abandonment Campaign Shell Removes 900-ft Parted Wireline from North Sea Well Setting a Critical Well Barrier in Tubing with Damaged Nipple Profiles

Retrieval of sub-surface safety valve (SSSV) with damaged fish neck

 

Technical Challenge:

Retrieval of sub-surface safety valve (SSSV) with damaged fish neck.

Well Type:

Oil producer (maximum 35 degree deviation).

Peak Solution:

7-in IN FRC heavy-duty pulling tool and the 5 1/2-in heavy-duty releasable spear.

Customer:

UK-based operator, North Sea

The Challenge:

An SSSV was changed out in 2007 and 2010 – taking three attempts to set on each occasion due to scale. In 2014, the well was shut in due to a failed SSSV test arising after an unsuccessful attempt to pull the SSSV to surface with the standard GS pulling tool. Damage to the fish neck was suspected to be the cause.

Considerations:

The following key requirements and concerns were identified:

  • Inability to retrieve and set new SSSV resulted in reduced production- a timely and effective solution was critical
  • The standard GS pulling tool would latch and shear down but failed to make full contact with the fish neck
  • The fish neck was suspected to be damaged
  • Training in the operation of Peak’s tools was required to ensure the full potential of the tools was realized 

Summary:

Peak’s 7” IN-FRC heavy-duty pulling tool has full radial contact allowing 30 percent more contact with the fish neck than a standard GS pulling tool. Fitted with serrated dogs for additional internal grip it was able to latch but pulled free from the fish neck on every attempt - this confirmed that damage to the fish neck was extensive.

It was therefore decided with the customer to use Peak’s 5 1/2-in heavy-duty releasable spear fitted with the long adjustment sleeve to ensure shear off capabilities should this be required. The viability of this option was proven following trials on a similar lock onshore to ensure latching was the best fit possible.

After a few attempts to latch it was found to be free to take a large overpull. With this confirming that the fish neck of the SSSV had successfully been latched, jarring commenced - the SSSV was successfully pulled to surface where severe damage to the fish neck was observed by the operators.

Value to Customer:

All operations were carried out safely and efficiently:

  • Failed SSSV now out of the well
  • New SSSV set and tested
  • Integrity issues now closed out
  • Well is open and shows an increase in production 
  • Peak Well Systems are now the primary fishing tool provider for the oil producer
  • The wireline crew have a better understanding of Peak's fishing tools following training
  • Post sale support coupled with proven operational reliability has created an excellent working relationship

 

Produce Code: 204, 210